My content
# | Title | Preview | Author | Groups | Updated |
---|---|---|---|---|---|
31 | 7 Day Work Week | How do you change the calendar to a 7 day work week versus 5? I have tried a number of things..changing the number of hours in a work week to 56, tell it there are more days per month...I don't see a way to just say there are 7 work days per week. I went to File, Calendar...as I want this to apply to the whole project. Should I change it somewhere else? Not sure where I should be looking. And, the changes I did make, didn't seem to make any difference anyway...the start/end dates didn't change in the Gantt chart when I change the number of days in the month or the number of working hou |
Lscouras | North American User Community | Apr, 16, 2015 |
32 | Maximum task Duraton | Hi Can anyone tell me if there is a maximim task/programme duration? I have a stage in a project wihch is likely to last 5000 days, but it seems the longest duration I can enter is 4166 Thanks in advance
|
Jon.barnett@ba… | European User Community | Apr, 13, 2015 |
33 | Removing times from Start/Finish Columns | Is there a way to remove the times in the Start and Finish columns, leaving only the dates? Thanks!!! |
zacharyvasquez | Global User Group | Mar, 31, 2015 |
34 | weeks gantt | Hi All, Anyone know how to set the gantt without the date. I wanto to see, for example: first week, second week etc... a sort of generic diagram, at the moment I dont know the starting date of the project. thanks |
pieretto | European User Community | Mar, 27, 2015 |
35 | I am new Beginner for Project Libre | Dear Friend. I am a Beginner with Project management and with Project Libre. Can any one provide the points which can help me to learn this tool. Plz plz plz Help me.
Regards, Anirudh
|
anirudha | Global User Group, Asian User Community | Mar, 12, 2015 |
36 | Docu for AddIn implementation | Greetings, I want to implement an AddIn for ProjectLibre, but I can't found a implementation documentation. Have everbody a link for me, with the implementation docu (API description, data structure (task, ressource, assinments), example framework for an AddIn, ... Thank you! Michael
|
Michael22 | Global User Group, European User Community | Mar, 12, 2015 |
37 | ProjectLibre named Sourceforge "project of the month" with interview | ProjectLibre was named Sourceforge's "project of the month". They have over 430,000 projects and have 4,800,000 downloads a day. We are very appreciative to be selected as it is great exposure. The ProjectLibre mission of offering an open source alternative is having an impact. We have been recognized at leading organizations and now have over 1,400,000 downloads. I was intereviewed for the project of the month process. |
OB | Mar, 10, 2015 | |
38 | Project Overview | Could someone please assist - new to Project Libre and wanted to know if the app can provide an overview of how one is performing against the programme scheduled. I know manually that we are 3 weeks behind schedule but how can I get Project Libre to indicate this |
[email protected] | European User Community | Mar, 09, 2015 |
39 | Remove Time from tasks? | I have seen quite a few posts in the past asking for an option to be able to remove the time from task views, but am unable to find if this feature has been implemented yet. Many posts about this subject date back to 2013 with an answer from the devs that they are going to implement this in a future release, but apparently has not yet (2 years later). |
Rhyno86 | North American User Community | Feb, 24, 2015 |
40 | compare estimated and actual timing | Hi there,
this is probably a simple question. I am planning a project and would be interested how much the timing turns out to deviate from the plan. I only see that I can first estimate the timing and change this by overriding the values. Can the first guess be saved and later be compared to how long it really took?
Thanks Heinrich |
GrabmayrH | Global User Group | Feb, 16, 2015 |