1 Few questions

Dear all,

I am new in using this software so I have a few questions about some funcionality:

1. Task information/Advanced       WBS- when codes are entered I don't see where are they used. Are they shown in some reports? Where?

2. Task information/Advanced      Type/Fixed Units- which units is this referred to?

3. Task information/Advanced      Type/Effort driven- don't realise how this impacts on enything. On what sections thas this apply?

4. Task information/Resources     Work countor- What are the differences in several options that can be chosen?

mihajlo fermevc Global User Group, European User Community Sep, 23, 2014
2 How to lock the duration of tasks

Hi everybody.

In my project, I have only one task (TASK1), and I think it will last for 10 days.

I assigned three resources to TASK1: Supervisor, Employee and a Diver.

pedrojo European User Community Sep, 23, 2014
3 collaborate in PL

We are starting some big projects and need to be able to collaborate on a project in real time on multiple machines. Being able to add tasks and what not on the fly. As we are a small company we have to be flexable. is there any support for this? we have tried but the updates dont seem to reflect once saved.

jollins European User Community Sep, 23, 2014
4 Question on adding fixed cost

How do you add a fixed cost to a task or resource (I'm using PL 1.5.5 on a Mac)? 

 

Thanks,

 

Wayne

lewisdw Global User Group, North American User Community Sep, 23, 2014
5 No available Drives within Projectlibre on Windowsclient

Hello there,

i'm started with PL on a Windows XP Client, 32 Bit, Java7-U21. After start PL, Unfortunately, i haven't any drives to save my project. Within Windows-Explorer or other Applications, i have all my drives to store/load my documents, within Projectlibre 1.5.4 no drives only Desktop is available! Can anybody help me?

Thanks Ralf

[email protected] European User Community Sep, 23, 2014
6 Hello World

Hi,

I am JP, the owner of the group "Project Controls"

I will start posting items soon. 

I will essentially talk about experience using ProjectLibre in professional environment, when project monitoring or project control techniques are used.

All ProjectLibre community members interested in such topics are welcome.

Take care,

 

JP

jp.tollenboom Sep, 23, 2014
7 Introduire une durée de "1 jour par mois pendant 1 ans"

 

Hello,
 
Would you tell me if it is possible to activity for a period of "one day per month for 1 year"
 
thank you
lordunreal European User Community Sep, 23, 2014
8 How to set precise end times for milestones?

Hi,

I just downloaded PL for testing on OpenSuse 12.1. I am thinking of using it for planning a school event. However, I ran into a critical problem. It seems impossible to set precise times for milestones, e.g. from 2013-03-19 10:00 to 2013-03-19 11:30. PL always resets the end time to 17:00. That's bad because it screws up the time tracking...

-Stefan

sgofferj Global User Group Jan, 28, 2016
9 Translations progressing rapidly and Japanese release of ProjectLibre UI

There has been a lot of progress on the documentation with ProjectLibre.  The community contributions are truly appreciated.  We do need more content added to the dccumentation.  You can access the English version here and add content.  We also just released a Japanese version of ProjectLibre.  The user interface was translated by community member Takahiro Morita.  Thank you Takahiro-san! We have lagged usage in Japan and this will certainly help the user community.

OB ProjectLibre Cloud Community, Global User Group, North American User Community, European User Community, Middle East User Community, African User Community, Asian User Community, South & Central American User Group Sep, 23, 2014