51 Any way to specify the range of a Gantt Chart for printing?

I have a project that runs from 10/1/12 ro 09/30/13. I'd like to print output that includes the Gantt chart only for 4/1/13 and following. Any way to do that? If not, please add  it to a "features request" list.

alexy Global User Group, North American User Community Sep, 23, 2014
52 Roll-up resources in a team?

Newbie to both project planning and PL here, So apologies if this is a dumb question. But I'm a believer that the only dumb question is the one you don't ask.

 

I have a resource called "Team A"

Indented under Team A, I have individual resources "Bob", "Cathy", and "David"

Task 1 is assigned to Team A, taking 120 hours to complete. Bob, Cathy, and David are interchangeable resources for this task, and can work concurrently on it.

Task 2 is assigned to Bob, takes 64 hours and starts at the same time as Task 1

alexy Global User Group, North American User Community Sep, 23, 2014
53 Gantt Chart Bar modifications All, Is there a way to remove the resource name from the Gantt Chart? I am new to ProjectLibre but in Microsoft Project I was able to right click on the bar in the Gantt Chart and edit the annotation that appeared on the Gantt Chart such as "replacing resource name with activity name" or " removing names off the bar chart all together". Any information you can provide to assist me would be greatly appreciated. Best Regards, Hec110 hec110 North American User Community Sep, 23, 2014
54 Few questions

Dear all,

I am new in using this software so I have a few questions about some funcionality:

1. Task information/Advanced       WBS- when codes are entered I don't see where are they used. Are they shown in some reports? Where?

2. Task information/Advanced      Type/Fixed Units- which units is this referred to?

3. Task information/Advanced      Type/Effort driven- don't realise how this impacts on enything. On what sections thas this apply?

4. Task information/Resources     Work countor- What are the differences in several options that can be chosen?

mihajlo fermevc Global User Group, European User Community Sep, 23, 2014
55 Multi-Project Gantt Chart?

Is there a way to view task start and finish dates for multiple projects?

kathbond North American User Community Sep, 23, 2014
56 Installing 1.5.5 on OS X 10.5.8 Leopard

Hello,

I work at a company that is just beginning to use ProjectLibre as a replacement for MS Project. So far it has been a hit with Windows our users, but I'm having trouble getting it going for one of our Mac users.

ScottCE North American User Community Sep, 23, 2014
57 How to lock the duration of tasks

Hi everybody.

In my project, I have only one task (TASK1), and I think it will last for 10 days.

I assigned three resources to TASK1: Supervisor, Employee and a Diver.

pedrojo European User Community Sep, 23, 2014
58 About the Initiative Projectlibre.

Introduction

The ProjectLibre, like its predecessor OpenProj, always aimed to be an alternative open source project management. The program as well as life follows its rhythm, is naturally evolve and old need to give way to the new. Unsurprisingly OpenProj is already past and ProjectLibre is the future, but we can not forget the way done at this point.

Overview: Initiative ProjectLibre

Hezequias Vasc… Global User Group Sep, 23, 2014
59 Moderation of Community ProjectLibre.

 

Hello,
 
What is needed to be a moderator in the Community ProjectLibre?
 
Thanks.
Hezequias Vasc… Global User Group Sep, 23, 2014
60 Keyboard Shortcuts

Has a list of keyboard shortcuts been published. If so can someone copy the shortcuts into this discussion? Thanks:)

raschalk Asian User Community Sep, 23, 2014