The ProjectLibre team has done significant work throughout Asia with our software.  There are almost a million users of our past software throughout the region.  The two co-founders have spent time in India, China, Japan and many other Asian countries.  We would like to have a robust community and have translated ProjectLibre into many languages.  We look forward to your joining the Asian User Group!  You can also join the Global and other user groups.

Asian User Community
Discussion

FF and SS Dependencies

0 comment(s)

Hi, I am just starting with project libre, and everything looks great, easy to use; Thanks for this great tool!!

Iam having a problem with task dependencies, and, if someone could help me, it would be great.

I ll try and explain it simply ))

Discussion

slelect finish date

0 comment(s)

When i select finish date on calendar, it  alway show yesterday, how to fix it?

Discussion

keyboard shortcuts

1 comment(s)

I have been using keyboard shortcuts and arrow keys in all the software I use since 1985, because they are faster than using the mouse or trackpad. I am wondering whether they could be developed for most commands in ProjectLibre, which is such a great system

Discussion

Translation issue with Chinese Simplified

2 comment(s)

My OS is Windows 10, defaulted language is Chinese Simplified.

I noticed that, in the resource sheet RBS was translated into a Bank, Royal Bank of Scotland ?!

However, we did not found any language option? Can we just choose to use the english version?

 

Discussion

Cost in INR in Project Libre

1 comment(s)

Hello All,

Discussion

Gantt Display

1 comment(s)

Hi,

I am a new user and just installed. I have an issue in gantt view where the days of the week are superimposed onto the dates themselves. Anybody come across this or is just me or my laptop.

Regards

Discussion

All projects in 'Project' screen

0 comment(s)

Hi all,

I'm  a new user of projectlibre and I am exploring the possibilities for professional use.

The thing I'm missing for now is the following:

Discussion

How is a task which missed deadline marked in the exported files?

1 comment(s)

Hi,

I want to know how the status of tasks which have missed their deadlines marked in the exported files like xml, etc.

I need to set up notifications on tasks which have missed deadlines, can I use any field say in the xml output which can help me get that?

Thanks,

Discussion

How to get notifications on late tasks so that the Resource working on it can be notified?

0 comment(s)

Hi,

Can anyone tell me if I can receive automated notifications about ProjectLibre on late tasks through e-mail, etc. so that the Resource working on it can be notified?

Thanks 

Dum

Discussion

Change language reports

1 comment(s)

i'm new user projetclibre and i want change the reports language it possible?

thanks a lot

JM