North American User Community

North American User Community

The ProjectLibre team was co-founded in Silicon Valley.  We have traditionally seen over 40% of the users in our open source projects come from the United States.  We will be posting NA specific information in the User Group.  You can join other groups as well if you are interested.

 

image group
Discussion

Roll-up resources in a team?

2 comment(s)

Newbie to both project planning and PL here, So apologies if this is a dumb question. But I'm a believer that the only dumb question is the one you don't ask.

 

I have a resource called "Team A"

Indented under Team A, I have individual resources "Bob", "Cathy", and "David"

Discussion

Gantt Chart Bar modifications

4 comment(s)
All, Is there a way to remove the resource name from the Gantt Chart?
Discussion

Multi-Project Gantt Chart?

3 comment(s)

Is there a way to view task start and finish dates for multiple projects?

Blog

Fixing the Finish date

1 comment(s)

Hi,

I am new to Project Libre.

1) Pls tell me how can I make the Finish date show as a fixed date-for some reason it rolls on.

Do I need to undo al the links between tasks?

Discussion

Quick question - answer may be obvious

3 comment(s)

I've got a quick question about ProjectLibre.  I want to set an absolute date for the Finish column and basically work backwards from that.  For example; an entire project has to be completed by, let's say, October 1.

Blog

Interview: "ProjectLibre edges in on Microsoft Project dominance"

0 comment(s)

"ProjectLibre edges in on Microsoft Project dominance"

Discussion

Installing 1.5.5 on OS X 10.5.8 Leopard

5 comment(s)

Hello,

I work at a company that is just beginning to use ProjectLibre as a replacement for MS Project. So far it has been a hit with Windows our users, but I'm having trouble getting it going for one of our Mac users.

Discussion

Calendar Start Time

3 comment(s)

I am running Linux Mint with ProjectLibre. I am trying to change the workday time. I can get to the screen required and create a Special Calendar, but ProjectLibre will not accept revised start and finish times.

Discussion

Question on adding fixed cost

2 comment(s)

How do you add a fixed cost to a task or resource (I'm using PL 1.5.5 on a Mac)? 

 

Thanks,

 

Wayne

Discussion

Multiple Users to Access One Project

2 comment(s)

We want to have multiple users update their individual task progress. My test shows multiple users can access one file, but no warning or other message appears to show if more than one person has the project file (.pod) open.