Discussion

Update task completion with actuals

8 comment(s)
How do I update a task that finishes ahead of schedule without having to change the planned duration? I've tried the obvious step of selecting a task and pressing the update button.
Discussion

Printing Resource Usage

1 comment(s)

I am new to ProjectLibre and want to know if the Resource Usage view can be printed to view what resources are needed when and how much per day - want to prevent overscheduling resources.

Thanks

 

Discussion

Microsoft project 2013 support

3 comment(s)

Hello

I am using ProjectLibre Version 1.5.7 for both Microsoft Windows 7 and Linux (Ubuntu).  Is it supported for Microsoft Project 2013 files?  If I load a 2013 file the UI gets stuck at the loading page. 

Thanks

Discussion

Project start date question

3 comment(s)

What is the earliest start date for a project that can be entered?

Discussion

How to create tasks with fixed duration (exactly 1 month)?

0 comment(s)

I am using PL to manage scientific projects.

I have projects with many fixed time tasks, such as exactly 1 month, exactly 3 months, exactly 1 year etc.

Blog

ProjectLibre awarded InfoWorld's "Best of Open Source"

2 comment(s)

I wanted to share the great news that InfoWorld has awarded ProjectLibre with the "Best of Open Source" or BOSSIE award.   We are really pleased and appreciative of the reco

Blog

bespoke production - how do you best use Project Libre?

0 comment(s)

I run a small bespke carpentry and joinery workshop with three prodcution staff and part time office staff.

Blog

Adjust the calendar's time increments

2 comment(s)

I've been asked to adjust the scale of the calendar to Months and weeks, instead of the default weeks and days.  This is for use with upper management.  Anyone know how to adjust the calendar's time scale?

Discussion

is there a .deb file available for download?

1 comment(s)

Or will I have to figure out how to convert the RPM? 

 

Thanks.

 

Discussion

Locating Error Output / Log File

2 comment(s)

Hi, Where does Error output go? I'm trying to automatically generate the initial project schedule. When I try to open the generated XML file, I get a progress bar and then nothing. How can I find out where the problem in the XML is?