How can I display the "DURATION" column in hours (instead of days)?

1 comment(s)

Gantt Chart:

My projects are rarely longer than a couple of days but I need to "drill down" to the hours and minutes for various disciplines so seeing the duration in "DAYS" doesn't help me... 

Discussion

Can I have a backward scheduled task in a forward scheduled project?

3 comment(s)

Quick question; I'm not sure I'm phrasing this right but, is there a way to have a backward scheduled task... in a forward scheduled project?  In other words; my project is primarily forward scheduled; where Task B is typically set to begin when the previous task (say: Task A...) is completed...

Discussion

Start and Finish Dates

1 comment(s)

If you put in the calendar that resources can only work 2 hours per day, the cost rolls up correctly yet on the Gantt chart when you put in the duration in days, the start and end dates are not calculated correctly (like they don't respond to the calendar modification of 2 hours per day).

Discussion

Change Font Color of Task

1 comment(s)

Is there a way to change the font color and/or background color of a task?

Discussion

Can I have multiple Hours Work by Day Settings?

2 comment(s)

I have a project with multiple people (resources) assigned to it.  One person can work on the project all day, but another can only work 4 hours per day.  How can I set that up in ProjectLibre?  

Blog

Multiple Projects Question

1 comment(s)

Is there a way to work with muliple projects as indivduals but combine them such as using a Master Project and sub-projects in MS Project?

Discussion

Changing Calendar Hours

2 comment(s)

I'm not sure if I missed something but I had a project that was built with the Standard 5-day calendar.  I changed it to six working days with the creation of a new calendar and saved it.  I then went into Resouces and changed the working hours of all workers, but the GANTT chanrt did not reflect

Discussion

Constraints Question

2 comment(s)

I'm new to ProjectLibre and have created a project and I want to know if there is a way to remove ALL time constraints from a task.

Blog

Google Drive

1 comment(s)

Can anyone tell me how to add Google Drive to the list of options when opening a .pod?  Thx.