261 How to change the calendar default work time frame ?

Hi, 

Does any guys know how to change the default work time frame? e.g. the default setting is from 8:00 ~ 12:00 to 13:00 ~ 17:00.

I knew the way to change it one by one per day , any seting could help for entire calendar ?

barkley.hsiao Global User Group Sep, 23, 2014
262 Problem open MS Project XML (Show Duration in 0)

Hi, when I try to open xml file from MS Project export, show me all duration in zero. But if I delete assigned resource show me correct duration.

I am testing version 1.5.2

thanks!! great job

Rodrigo Guerrero

rguerrero Global User Group Sep, 23, 2014
263 Undo / Redo

Right now the standard (on windows) ctrl-z / ctrl-y do not perform the Undo/Redo. Because those particular shortcuts are so common, I find it very distracting that they do not work in ProjectLibre. Maybe I just type and click too fast, but I rely on undo pretty heavily and it really slows me down to have to hit the button.

 

marcel123 Global User Group Sep, 23, 2014
264 How to change number of workdays per week?

Hi All

 

I have just started using Project Libre. I would like to change the number of work days from the default 5 to 6 (Saturdays are also working days). I am not able to get this information from the on-line help

How to do this?

Thanks in advance

Regards Ganesh

 

 

M.Ganesh Global User Group Sep, 23, 2014
265 Unable to change task dates

I am unable to change the start dates for tasks once they have been linked - even after the link is removed.

I have tried adding a new task before the existing ones with a new date, then linking to the existing tasks - there is no change to the existing dates.

I have noted a number of posts in other forums on this issue, but none here. It would appear to be a common problem. Any suggestions would be greatly appreciated.

Dave

 

 

DaveB Global User Group Sep, 23, 2014
266 Save in xml microsoft format

I use ProjectLibre 1.5.1. I saved in xml format a test exercise with task-Resource assignment.

I compared node element Assignment with especification xml microsoft --> "http://msdn.microsoft.com/en-us/library/office/bb968611%28v=office.12%29.aspx". I saw node element /Assignment/UID is a node required to Microsoft but when I save in ProjectLibre don't use these node. Is normal? Can be ProjectLibre use another Microsoft especification?

Regards,

 

 

dgarcia European User Community Sep, 23, 2014
267 80,000 downloads and the community is growing rapidly

The open source movement is growing rapidly.  ProjectLIbre is a shining light for the impact open source can have around the world competing against proprietary software.  ProjectLibre now has more than 80,000 downloads in essentially every country in the World covered in this usage.  Our reach is powerful with the open source model.  We are getting many language translations and downloads are extremely distributed, only 20% of the downloads are in the United States.  I will post another blog shortly that further discusses the regional and global impact  of ProjectLibre and open source.

OB ProjectLibre Cloud Community, Global User Group Sep, 23, 2014
268 Out of sequence tasks done but project end date doesn't move

Really enjoying using this program, good work!

I have a question on the way the program handles the project end date.  If I have 3 tasks a,b and c.

If they all have 10 days duration and are setup up so when 'a' finishes, 'b' can start and then when 

 'b' finishes 'c' starts.  This means that the project will have a duration of 30 days.  If 'b' is then finished 

 and set to being 100% complete before 'a' has finished, the project end date is not brought in.  It just

 leaves a space.  Can this not be done automatically?

 

cchalmers Global User Group Sep, 23, 2014
269 Block out holiday and show grids when printing

So, I'm a newbie here, I have created by programme spreading over several months.

Firstly I need to block out Xmas holidays - any ideas?

Second, I would refer to show the grid when printing. I can show rows, but can't find a show columns button anywhere - any ideas on this one as well?

 

cheers,

Alec

alec smith European User Community Sep, 23, 2014
270 Resources

Hi,

 

is it possible to express the resource usage in a project where a person is used 10% from time t1 to t2, 100% from t2 to t3, anf 60% from t3 to t4???

SG

SG European User Community Sep, 23, 2014